Site Events

Coppervale Creek Civil Package · Coppervale Resources Ltd

6 events

1

High

3

Medium

2

Low

6 total

eot_variationHigh14 Apr 2026

Weather delay: 32mm overnight rainfall caused Section B access track to become unworkable until 1400hrs. Drain lines waterlogged and unable to be trimmed to grade. Supervisor has flagged this as potential EOT event pending further delay days and program impact to Section B drainage sequence.

Recommended Action

Commence contemporaneous EOT documentation immediately. Record: (1) actual rainfall data and source, (2) site conditions preventing access/works, (3) hours/productivity lost, (4) crew redeployment details, (5) daily weather monitoring through remainder of week. Photograph waterlogged conditions and inaccessible areas. Prepare draft EOT notice if delays extend beyond today. Notify PM of potential critical path impact to Section B drainage sequence.

scheduleMedium14 Apr 2026

Section B table drain works suspended for majority of day due to weather. Supervisor noted program impact to drainage sequence and potential critical path delay requiring reassessment once full week's weather is known.

Recommended Action

Update project schedule to reflect actual delay to Section B works. Conduct critical path analysis at week's end to determine float consumption and downstream impacts. Monitor weather forecast and prepare recovery plan if window opens. Document all schedule impacts contemporaneously for potential EOT claim substantiation.

commercialLow14 Apr 2026

Crew redeployed to Section A culvert headwall formwork and general site tidy during weather delay. Unplanned resource allocation may have cost implications depending on contract structure and whether weather delay is compensable.

Recommended Action

Verify contract weather provisions (is rainfall compensable? what is the threshold?). Track actual crew hours against Section A works vs. planned Section B works. If weather delay is compensable under contract, ensure time records clearly distinguish between productive redeployment and genuine standing time. Confirm whether formwork acceleration to Section A impacts overall program strategy.

plant_idleMedium24 Apr 2026

Padfoot roller (Plant No. 7) suffered hydraulic fault at approximately 1330 hours, resulting in 3.5 hours lost productivity. Unit down for remainder of shift with no backup roller available on site. Mechanic booked for tomorrow morning.

Recommended Action

Document plant downtime for daily EOT records. Confirm mechanic attendance tomorrow AM and estimated return-to-service time. Consider requesting client approval for backup plant if repairs extend beyond midday tomorrow. Track cumulative impact on Section B pavement program.

scheduleMedium24 Apr 2026

3.5 hours lost pavement base course productivity in Section B (CH500-CH800) due to plant breakdown. Crew reallocated to culvert headwall finishing and site clean-up.

Recommended Action

Update Section B pavement program to reflect lost productivity. Confirm revised completion forecast for CH500-CH800 base course works. Monitor cumulative schedule impact if plant repairs extend into tomorrow afternoon. Advise PM of potential catch-up measures required.

commercialLow24 Apr 2026

No backup padfoot roller available on site during Plant No. 7 breakdown, resulting in 3.5 hours crew standing time (reallocated to non-critical works). Potential claim for inefficiency/disruption costs if this represents inadequate plant redundancy under the contract.

Recommended Action

Review contract plant schedule requirements — does the contract require backup/redundant compaction plant? If breakdown extends beyond tomorrow midday, consider flagging potential disruption claim for lost efficiency. Document crew reallocation and any non-productive time.