Program Health

Coppervale Creek Civil Package

New Entry

Schedule Summary

23

Total

14

Critical

61%

5

At Risk

22%

4

On Track

17%

Key Milestones(4)

Milestone — Earthworks Complete Section A

13 Mar 2026

Critical

Milestone — Practical Completion Whole of Contract

8 May 2026

Critical

Milestone — Section A Practical Completion

6 Apr 2026

Critical

Milestone — Section B Practical Completion

8 May 2026

Critical

By Discipline

NameTotalCritRiskOK
EARTHWORKS
7520
PAVEMENTS
4400
CULVERTS
3210
SEALING
2200
PROJECT MANAGEMENT
1100
DRAINAGE
2020
ELECTRICAL
4004

By Zone

NameTotalCritRiskOK
ZONE A-3
6312
ZONE B-3
5302
ZONE A-2
4220
ZONE B-2
4220
ZONE A-1
2200
ZONE B-1
2200