Daily Report (Agent 1)

notes

Significant out-of-scope instruction received from client representative. Works have proceeded under verbal direction. Commercial action required.

weather

Not recorded

hse notes

No incidents reported

entry date

2026-07-29

project id

9c85ac41-a317-4364-bae2-4f1167656cc4

qaqc notes

ITP inspections conducted

plant summary

Not recorded

cause of delay

Client instruction — out-of-scope grading works directed by Lawrence Chang

works location

CH1200 - CH2000

works performed

General grading, rolling, and road construction works undertaken at CH1200-CH2000.

personnel summary

Not recorded

decisions required

PM approval required for VIRF and potential variation claim relating to out-of-scope works directed by client representative

out of scope works

Approximately 5,000 m² road section grading and construction directed by Lawrence Chang — outside contract scope

client instructions

Lawrence Chang directed contractor to grade and construct new road section (approx. 5,000 m²) outside original contract scope

materials delivered

25 m³ concrete delivered to site

progress vs program

Behind program due to client-directed out-of-scope works

Detected Events (4)

highvirfVIRF

Client representative Lawrence Chang verbally instructed contractor to grade and construct new road section (approximately 5,000 m²) outside original contract scope at CH1200-CH2000. Works proceeded under verbal direction.

Recommended Action

Generate VIRF immediately documenting Lawrence Chang's verbal instruction. Obtain written confirmation of instruction and authority. Prepare cost and time estimate for variation claim. Escalate to PM for commercial review and client notification.

highscopeVIRF

Out-of-scope works identified and directed by client: approximately 5,000 m² road section grading and construction outside contract limits. Works directed verbally by Lawrence Chang.

Recommended Action

Issue formal scope clarification letter to client identifying works as outside contract scope. Request written confirmation of instruction and authority. Prepare detailed cost breakdown and program impact assessment. Do not proceed further without written client confirmation and commercial agreement.

higheot_variationVIRF

Schedule impact due to client-directed out-of-scope works. Program now behind due to additional works instruction outside original contract scope.

Recommended Action

Quantify time impact of out-of-scope works on critical path. Prepare EOT claim submission with detailed program analysis showing delay caused by client instruction. Document all associated costs (labour, plant, materials, preliminaries extension). Submit formal variation and EOT claim package to client.

highcommercialVIRF

Significant commercial event: client has directed substantial out-of-scope works (5,000 m² road construction) without written instruction or commercial agreement in place. Contractor has proceeded under verbal direction creating commercial risk.

Recommended Action

Immediate PM escalation required. Halt further out-of-scope works until written instruction and commercial terms agreed. Issue formal commercial letter documenting: (1) works are out of scope, (2) works undertaken under verbal instruction only, (3) contractor reserves all rights to claim cost and time, (4) request immediate written confirmation and commercial agreement before proceeding further. Prepare detailed cost estimate for variation claim. Consider contractual remedies if client disputes liability.

Commercial Letter Draft

VIRFRE: Huntly Road Upgrade — Verbal Instruction for Out-of-Scope Works and Notice of Extension of Time / Variation Claim

Dear Sir/Madam, We refer to works undertaken on 29 July 2026 at the Huntly Road Upgrade project, specifically within the section CH1200 to CH2000. We advise that your representative, Mr Lawrence Chang, verbally instructed the Contractor to grade and construct a new road section of approximately 5,000 m² in this area. These works fall outside the limits and scope of the original Contract and were not included in the agreed Contract Documents. Notwithstanding the absence of written instruction, the Contractor proceeded with these works on the basis of the verbal direction given, in order to avoid delay to the Client's operations. This letter serves as a Verbal Instruction Report and Field Record (VIRF) to formally document the instruction given. The Contractor requests that the Client Representative provide written confirmation of this instruction, together with confirmation of the authority under which it was issued, within seven (7) days of the date of this letter. The Contractor further wishes to place on record that the works described above constitute out-of-scope works under the Contract. Accordingly, the Contractor reserves its full rights to claim additional costs and time associated with the performance of these works, including but not limited to labour, plant, materials, and extended preliminaries. The Contractor will not proceed with any further out-of-scope works beyond those already completed without written instruction and prior agreement on commercial terms. As a direct consequence of the above instruction, the Contractor's program has been adversely affected, with progress now recorded as behind schedule. The Contractor hereby gives notice to the Principal of a potential Extension of Time claim arising from this event. A detailed program impact assessment and supporting cost documentation will be prepared and submitted in due course in accordance with the Contract. Given the scale and commercial significance of this instruction, the Contractor considers it prudent to formally record the circumstances of this event and to seek the Client's written confirmation and commercial agreement before any further works of this nature are undertaken. This record is made to document verbal instructions given by the Client Representative. The Contractor reserves the right to claim additional cost and/or time associated with compliance with this instruction. We would appreciate your prompt attention to this matter and look forward to your written response confirming the instruction and agreeing a path forward for the associated variation and time claims. Yours faithfully, [Contractor Representative]

From the Field — Operator Entries

Submitted by operators for Wednesday 29 July 2026 via Timekeeper.

1 to approve

2

Operators

17.98

Labour h

2

Machines

Chris Gordon

06:0017:30

11.50

Labour h

Released

Hi, steering hydraulic hose broke fucking thing

AssetSMU startSMU finishHours
STCGR0012000.02010.010.00
Breakdown

Released 29/07/2026, 4:35:57 am — this timesheet feeds the pay-period summaries and can no longer be amended.

Jo Smith

06:1712:46

6.48

Labour h

Submitted
AssetSMU startSMU finishHours
DEMO-GR-0142004.02007.03.00

Captured in Timekeeper by the operator on site. Approve to sign the hours off; amend to correct them — the operator's original submission is always kept alongside. Releasing locks a timesheet and feeds the pay-period summaries. Operators are managed in Timekeeper.

Progress vs Program

Behind

yeah we just haven't looked at see how the schedule goes yeah potential client delay

Cause of Any Delay

Reason
Client instruction
Detail
if I came out and asked us to go engrade a new section of road that's not even scope

Resources

All resources available?
Yes

Works Performed

Location / Chainage
CH1200 - CH2000
Works
are you just general grading rolling constructing Road

Out-of-Scope Works

Yes
Directed by
Lawrence Chang
Detail
work a section of road at least 5000 square metres edition

Client Instructions

No

QAQC

yeah ITP inspections

HSE

No

Materials

MaterialQtyUnitType
concrete 25m3delivered
Created 29/07/2026, 4:34:44 am