Project now behind schedule due to weather delay. One full productive day lost on 23/06/2026.
Recommended Action
Update project schedule showing 1-day delay impact. Assess critical path impact. Communicate revised completion forecast to PM and client. Link schedule delay to EOT claim. Monitor for flow-on impacts to subsequent activities.
Weather delay - storm event on 23/06/2026 resulted in site shutdown after 1 hour of work. Client Representative restricted site access due to weather conditions. Crew (3 personnel) and plant (digger) mobilised but stood down for remainder of day.
Recommended Action
Document as potential EOT event. Weather may qualify as inclement weather under contract. Client's direction to cease work and restrict access compounds delay. Capture: (1) weather bureau data for the day, (2) site photos showing conditions, (3) crew time sheets showing mobilisation, (4) plant hire costs for idle time. Calculate standing time costs for commercial claim evaluation.
Client Representative Mr Bob verbally instructed site shutdown at 10:21hrs on 23/06/2026 due to inclement weather and restricted site access. Work ceased for remainder of day.
Recommended Action
Generate VIRF immediately. Document client-directed shutdown. Prepare EOT claim for weather delay day (1 day lost). Attach weather data and this VIRF to EOT submission. This record is made to document verbal instructions given by the Client Representative. The Contractor reserves the right to claim additional cost and/or time associated with compliance with this instruction.
Site shutdown for full day due to inclement weather (storm conditions) and client restriction of site access. Approximately 1 hour of work achieved before cessation. Personnel on site for full shift (10h) but unable to perform contracted works.
Recommended Action
Prepare EOT claim for 1 day weather delay. Document: (1) Weather conditions via BOM data, (2) Client instruction to cease work (VIRF), (3) Site access restriction by client, (4) Personnel costs incurred (3 crew × 10h each), (5) Plant idle time (Digger 8h idle). Calculate standby costs for crew and plant. Submit formal EOT notice within contractual timeframes.
Client Representative Mr Bob verbally instructed site shutdown at 10:21 on 23/06/2026 due to inclement weather and restricted site access. Work ceased after first hour of operations.
Recommended Action
Issue formal VIRF to document verbal instruction. Instruction resulted in full day shutdown with crew and plant mobilised but unable to work. Preserve all time records and costs associated with this shutdown period.
Full day disruption on 23/06/2026 - crew of 3 mobilised and on-site for 10 hours each, but only 1 hour productive work achieved due to weather and client access restrictions. Potential standing time claim for labour and supervision.
Recommended Action
PM to assess commercial impact: 3 crew × 9 hours unproductive time due to weather shutdown. Determine if weather qualifies as 'inclement weather' under contract definitions. If Client's access restriction was the determining factor (rather than contractor's assessment of safe working conditions), this strengthens EOT/cost recovery position. Prepare cost impact summary for client notification.
Digger stood idle for 8 hours (89% downtime) on 23/06/2026 due to client-directed weather shutdown. Only 1 hour active work achieved before shutdown order.
Recommended Action
Capture plant idle time costs. Digger hire continues during weather standdown. Document in conjunction with EOT event above - this is a quantifiable cost impact of the weather delay and client access restriction. Include in commercial assessment.
Personnel costs incurred for full shift (3 crew × 10 hours each = 30 man-hours) with minimal productive output due to client-directed weather shutdown and site access restriction.
Recommended Action
Calculate and document standby labour costs: 1× Super (10h), 1× Electrician (10h), 1× Labourer (10h). Include in EOT claim cost submission. Only ~1 hour of these 30 man-hours was productive due to client instruction to cease works.
Digger standing idle for 8 hours (89% idle time) due to client-directed weather shutdown. Only 1 hour productive use achieved.
Recommended Action
Capture plant standby costs for EOT/variation claim. Document 8 hours idle time at applicable idle rates. Link to weather delay event and client instruction VIRF. Include in delay cost calculation.
Generate a formal commercial letter based on the 9 detected events above.
Submitted by operators for Tuesday 23 June 2026 via Timekeeper.
No operator entries for this date yet.
Hours submitted from the field will appear here automatically.
Captured in Timekeeper by the operator on site. Approve to sign the hours off; amend to correct them — the operator's original submission is always kept alongside. Releasing locks a timesheet and feeds the pay-period summaries. Operators are managed in Timekeeper.
So I'll use this inclement weather today couldn't get the site