HSE NoticeRE: [Project Name] — HSE Incident Notification and Client-Directed Work Stoppage

Dear Sir/Madam, We write to formally notify you of a workplace incident that occurred on site on 10 May 2026, and to document the subsequent verbal instruction issued by your representative. HSE Incident At approximately [time], an operator sustained a medical treatment injury when stepping down from an excavator, rolling their ankle severely. The injured worker was immediately provided first aid on site and subsequently transported to the local hospital for medical treatment. A formal incident investigation is currently underway in accordance with our safety management procedures and WHS regulatory requirements. Verbal Instruction - Work Stoppage At 12:32 hours on 10 May 2026, your Client Representative MR W issued a verbal instruction for an immediate safety pause to reset the work crew and review working areas and housekeeping standards across the site. This instruction resulted in a complete work stoppage of 9 hours duration. This record is made to document verbal instructions given by the Client Representative. The Contractor reserves the right to claim additional cost and/or time associated with compliance with this instruction. Extension of Time Notice We hereby put the Principal on notice of a potential Extension of Time claim arising from the client-directed work stoppage. While we acknowledge that reasonable incident response time is part of our safety obligations, the extended 9-hour safety pause directed by your representative constitutes a compensable delay event under the contract. The work stoppage resulted in: - 31 hours of personnel standing time across 3 crew members - Standing time for 2 plant items (excavator and grader) - Loss of 9 hours scheduled production - Impact to the critical path and project program Commercial Impact The Contractor reserves its rights to claim additional time and cost associated with the client-directed work stoppage, including but not limited to standing time costs for personnel and plant, and any consequential delays to the project completion date. We will provide you with a detailed time impact assessment and cost substantiation in due course. We trust that normal operations can resume following completion of our incident investigation and implementation of any additional safety measures deemed necessary. Yours faithfully, [Contractor Representative]

From the Field — Operator Entries

Submitted by operators for Sunday 10 May 2026 via Timekeeper.

No operator entries for this date yet.

Hours submitted from the field will appear here automatically.

Captured in Timekeeper by the operator on site. Approve to sign the hours off; amend to correct them — the operator's original submission is always kept alongside. Releasing locks a timesheet and feeds the pay-period summaries. Operators are managed in Timekeeper.

Progress vs Program

Behind

1. Weather 2. Incident: lost 9 hours due to stop work and reset after incident

Cause of Any Delay

Reason
Personnel
Detail
Incident and stop work

Resources

All resources available?
Yes

Personnel on Site

NameRoleHours
Marcus FelthamPM9
Brett HalvorsenOperator11
Sam IoaneOperator11

Plant on Site

ItemActive hIdle hBrkdn
diggerN
graderN

Works Performed

Location / Chainage
on site
Works
gardening and flower potting

Out-of-Scope Works

Client Instructions

Yes
Given by
MR W
Time
12:32:00
Instruction
Safety pause to reset the work crew and ensure they are reviewing the working areas and house keeping -

QAQC

inspection of pre-clearing

HSE

Yes
Incident type
medical-treatment
Description
operator when going to step down off digger, has rolled their ankle severely and was taken to medic and then on to local hospital.

Decisions & Discussions

client intervened and requested a stop work safety pause and for teams to address housekeeping and slips and trips