Commercial Letter Draft

VIRFRE: Project Works — Verbal Instruction Record Form and Formal Notices

Dear Sir/Madam, I refer to the verbal instruction given by your Client Representative, Stuart Barnes, at approximately 05:09 hours on 11 May 2026. VERBAL INSTRUCTION RECORD This letter serves as formal record of the following verbal instruction: Date: 11 May 2026 Time: 05:09 hours Client Representative: Stuart Barnes Instruction: Cease contracted scope works and perform detailed earthworks at Ch209 Resources Directed: Two operators, one excavator, and one spotter Estimated Duration: Two days OUT-OF-SCOPE WORKS NOTICE We hereby notify you that the detailed earthworks at Ch209 fall outside the contracted scope of works. The Contractor has commenced these works under your direct instruction, however we formally reserve our rights to claim additional time and cost for: • Labour costs for two operators over two days (24 man-hours per day) • Plant hire for excavator including 2 hours idle time caused by the scope change • Spotter costs for the duration of the works • Site overheads and margins • Disruption costs arising from interruption to planned contracted works EXTENSION OF TIME NOTICE We hereby put the Principal on notice of a potential Extension of Time claim arising from this client-directed scope change. The instruction to cease contracted works and perform out-of-scope activities has caused a program delay of approximately two days. Our project status is now behind program as a direct result of this interruption to planned works sequence. The Contractor requests written confirmation of this variation and approval to proceed with the out-of-scope works beyond the initial two-day period if required. This record is made to document verbal instructions given by the Client Representative. The Contractor reserves the right to claim additional cost and/or time associated with compliance with this instruction. Yours faithfully, [Contractor Representative]

From the Field — Operator Entries

Submitted by operators for Monday 11 May 2026 via Timekeeper.

No operator entries for this date yet.

Hours submitted from the field will appear here automatically.

Captured in Timekeeper by the operator on site. Approve to sign the hours off; amend to correct them — the operator's original submission is always kept alongside. Releasing locks a timesheet and feeds the pay-period summaries. Operators are managed in Timekeeper.

Progress vs Program

Behind

Client out of scope works

Cause of Any Delay

Reason
Client instruction
Detail
Client requested out of scope works approximately two days

Resources

All resources available?
Yes

Personnel on Site

NameRoleHours
Brett HalvorsenOperator12
Sam IoaneOperator12

Plant on Site

ItemActive hIdle hBrkdn
Digger102N

Works Performed

Location / Chainage
Ch209
Works
Minimum works performed due to client interrupting scope work to go into works for him

Out-of-Scope Works

Yes
Directed by
Stuart Barnes
Detail
Client requested approximately two days worth of work of detailed earthworks with two operators and a greater and spotter

Client Instructions

Yes
Given by
S Barmes
Time
05:09:00
Instruction
As above get the information from the outer scope work

HSE