Fri, 24 Apr 2026
Pavement base course continuing Section B, CH500-CH800.
Tue, 14 Apr 2026
Table drain works Section B suspended for most of the day.
Wed, 18 Feb 2026
Bulk earthworks continuing Section A, cut to fill progressing CH0-CH300. Subgrade trim commenced on …
Mon, 16 Mar 2026
Culvert installation continuing CH0-CH500, headwall formwork commenced on completed culverts.
Fri, 27 Mar 2026
Pavement base course continuing Section A, CH0-CH400 complete and compacted. Prime and seal prep und…