Variation Flags

Huntly Road Upgrade · Huntly District Council

0

Pending

0

Sent

10

PM Approved

10 total

PM Approved (10)

VIRF-010
PM Approved

Verbal instruction — see attached commercial letter

Issued byTo be confirmed
Raised26 July 2026(19d ago)
Instruction date10 May 2026
From journal entry — 10 May 2026
VIRF-009
PM Approved

Verbal instruction — see attached commercial letter

Issued byMr HanRoy
Raised24 July 2026(21d ago)
Instruction date9 May 2026
From journal entry — 9 May 2026
VIRF-008
PM Approved

Verbal instruction received from Angie Doyle (Client Representative) at 19:55 to relocate digger and perform alternate work. Supervisor notes scope status is uncertain ('might be a variation I'm not sure'). Instruction diverted plant from programmed culvert excavation works.

Issued byAngie Doyle
Raised9 June 2026(66d ago)
Instruction date9 June 2026
From journal entry — 9 June 2026
VIRF-007
PM Approved

Client Representative (SpongeBob) verbally instructed all works to cease at 08:30hrs pending Engineer re-testing of ball embedment tests due to discrepancy in results between 01 June and 02 June testing.

Issued bySpongeBob
Raised4 June 2026(71d ago)
Instruction date2 June 2026
From journal entry — 2 June 2026
VIRF-006
PM Approved

Program delay caused by excavator breakdown and unavailability of parts. Three form workers stood idle unable to commence works pending excavation completion. Full day production lost on excavation activity. Delay attributed to parts not being organised/ordered in advance.

Issued byBilly Bob
Raised2 June 2026(73d ago)
Instruction date2 June 2026
From journal entry — 2 June 2026
VIRF-005
PM Approved

Latent site condition encountered at CH 6.500 — hard rock material below RL 142.5 not indicated in contract geotechnical investigation report. Material requires hammer attachment and is causing significant production delay (30% of expected rate). Critical path activity impacted. Initial notice issued per Schedule 3.

Issued byRoger Rickerby
Raised30 May 2026(76d ago)
Instruction date30 May 2026
From journal entry — 30 May 2026
VIRF-004
PM Approved

Material placement at CH 7.200 proceeding without formal source approval as required by specification. NATA verification compaction testing requested post-placement — results expected within 48hrs. Potential NCR if material fails to meet specification requirements.

Issued byJohn Smith
Raised30 May 2026(76d ago)
Instruction date30 May 2026
From journal entry — 30 May 2026
VIRF-003
PM Approved

Verbal instruction from Roger Rickerby (Superintendent) at 1430 to extend pavement widening 200m past CH 12.000 to tie into McPhee Road junction for traffic safety. Superintendent requested crew to 'just keep going' through tomorrow. No written direction received.

Issued byTo be confirmed
Raised30 May 2026(76d ago)
Instruction date30 May 2026
From journal entry — 30 May 2026
VIRF-001
PM Approved

Client Representative Barry Brush verbally instructed additional works to construct new footpath. Client has requested additional 3 days on program. This record is made to document verbal instructions given by the Client Representative. The Contractor reserves the right to claim additional cost and/or time associated with compliance with this instruction.

Issued byBarry Brush
Raised12 May 2026(94d ago)
Instruction date11 May 2026
VIRF-002
PM Approved

Verbal instruction to re-align kerb line at chainage 1+400 to avoid existing tree root system. Client Representative directed change on site.

Issued byBarry Brush
Raised11 May 2026(95d ago)
Instruction date10 May 2026