Huntly Road Upgrade · Huntly District Council

29 entries

Operator hours with no journal entry

The field submitted hours for Sat, 25 July 2026, but no journal entry exists for that date. Add the entry and the field data appears on it automatically.

Add a journal entry →

Wed, 12 Aug 2026

AI DoneBehind

Rehab to laydown area receding and spreading topsoil Prepping for Covid installation Windsor too hig

View entry →

Sun, 9 Aug 2026

AI DoneAhead

No works recorded

View entry →

Thu, 30 July 2026

AI DoneOn Track

Yeah working from SLK17 to 171 working our way north crew crew B

1 from field · 12.00hView entry →

Wed, 29 July 2026

AI DoneBehind

are you just general grading rolling constructing Road

2 from field · 17.98hView entry →

Sun, 26 July 2026

AI DoneOn Track

scope work - demo entry

2 from field · 22.00hView entry →

Tue, 23 June 2026

AI DoneBehind

No works recorded

View entry →

Tue, 9 June 2026

AI DoneBehind

limited due to digger breakdown / client not attendance inspection

View entry →

Tue, 9 June 2026

AI DoneOn Track

Excavating culvert

View entry →

Tue, 9 June 2026

AI DoneOn Track

No works recorded

View entry →

Tue, 2 June 2026

AI DoneBehind

Team set up TMP and had to tractor brooms sweep the basecourse

View entry →

Tue, 2 June 2026

AI DoneBehind

Yeah, three chippy stood around waiting because they couldn’t get the excavation done. Digger was br

View entry →

Sat, 30 May 2026

AI DoneAhead

Daily pre-start completed. Toolbox on working adjacent to light traffic on the eastern shoulder. No

View entry →

Sat, 30 May 2026

AI DoneBehind

Cut excavation CH 6.500 — partial. Rock material exposed and being worked with standard bucket. Prod

View entry →

Sat, 30 May 2026

AI DoneBehind

Embankment construction . Cut-to-fill operation hauling material from CH 6.500 cut area direct to fi

View entry →

Fri, 29 May 2026

AI DoneOn Track

Pavement widening CH 11.400 to CH 11.850. Subgrade trim, moisture conditioning, compaction. NATA tes

View entry →

Thu, 14 May 2026

AI DoneBehind

Grace up Access through the dealership drain, tidy up existing cleared track and strip veg at the tr

View entry →

Thu, 14 May 2026

AI DoneBehind

No works recorded

View entry →

Tue, 12 May 2026

AI DoneBehind

one excavator parked up ex 12 working night shift loading two times boxes ranked the 209 borrow Pitt

View entry →

Mon, 11 May 2026

AI DoneBehind

continued to construct decking and installationof footings and posts operator cleared site and prepp

View entry →

Mon, 11 May 2026

AI DoneBehind

Minimum works performed due to client interrupting scope work to go into works for him

View entry →

Mon, 11 May 2026

AI DoneBehind

No works recorded

View entry →

Sun, 10 May 2026

AI DoneBehind

gardening and flower potting

View entry →

Sun, 10 May 2026

AI DoneBehind

gardening and flower potting

View entry →

Sun, 10 May 2026

AI DoneBehind

No works recorded

View entry →

Sat, 9 May 2026

AI DoneBehind

ramp construction for client at the station intersection

View entry →

Sat, 9 May 2026

AI DoneBehind

No works recorded

View entry →

Fri, 8 May 2026

AI DoneBehind

Earthworks continued Ch 1200–1235. Subgrade trim and compact completed Ch 1220–1235 to design RL. Se

View entry →

Fri, 8 May 2026

PendingBehind

No works recorded

View entry →

Sun, 26 Apr 2026

PendingOn Track

No works recorded

View entry →